By next week (July 18) we will be finished with Phase I and beginning Phase II. The current schedule looks like this:
The Project Phases:
Phase I (May - July 18 2008): Units 11- 28 and 65-68 and 127-130B (please note that Units 25-28 and 130B have been moved to the end of Phase II and Units 43-46 have been put in Phase I)
Phase II (July 15 - October 1, 2008) Units 47-50 and 79-90 and 109-126 and 25-28 and 130B
1 comment:
Slow Down! We need it to be right, not fast. I have heard there are some problems occurring with the soffet areas as well as sloppy trim and door work.