Hello Homeowners - when we originally bid out the Staining Project we considered that it might take 4 years to complete - primarily due to funding issues. As it turned out the pricing and performance offered by Oliver have permitted us to greatly accelerate the time line. So much so that we might be able to get into at least part of Phase III this year.

By next week (July 18) we will be finished with Phase I and beginning Phase II. The current schedule looks like this:

The Project Phases:

Phase I (May - July 18 2008): Units 11- 28 and 65-68 and 127-130B (please note that Units 25-28 and 130B have been moved to the end of Phase II and Units 43-46 have been put in Phase I)

Phase II (July 15 - October 1, 2008) Units 47-50 and 79-90 and 109-126 and 25-28 and 130B